scheduled for completion this week. Work is now
concentrated on pouring the main floor level
concrete and concrete columns. The next week
we should see the pouring of the concrete
retaining walls near the gym.
Remember that additional parking is available,
thanks to the owner, at the commercial parking
area on Oakgate Drive. Use this when you can to
make the closer spaces available for those who
cannot walk that distance. Updated time lapse
videos, and new drone fly-overs and still
photographs are available for all to view at
https://spaces.hightail.com/space/
VrhVBgbwuB. (This gives you the very best
view of the construction activity.